706–752 Mamre Road, Kemps Creek NSW · SSD-92743706 · 1 GW · 52 ha
Proposed connection: three lead-ins from Transgrid's Sydney West 330 kV substation
N-1 firm transformer capacity at the Sydney West Bulk Supply Point. Sydney West has been in firm-capacity deficit since 2025/26, before this project is added. Transgrid's own RIT-T puts the gap between forecast maximum demand and N-1 firm transformer capacity at 48 MVA in 2025/26, rising to 791 MVA by 2032/33. The committed remedy is a single 375 MVA transformer. The deficit is already larger than the fix.
A 1 GW load is roughly 1,050 MVA at 0.95 power factor, which is more than the entire forecast 2032/33 shortfall again.
The frequently cited Kemps Creek BSP does not resolve this. It is real, funded and committed, but it was scoped to relieve the Macarthur 132 kV BSP and serve Aerotropolis distribution growth. It is not a transmission connection asset for a gigawatt load at Sydney West.
Transgrid publishes the firm-capacity gap at two points in time. Intermediate years are not published, so only the two stated values are shown. The remedy and the site load are placed on the same axis for comparison.
From Transgrid's RIT-T Maintaining reliable supply to Western Sydney, commenced as a reliability corrective action under Schedule 5.1.4 of the National Electricity Rules.
| Measure | Value | Grade |
|---|---|---|
| Demand vs N-1 firm transformer capacity | Forecast demand exceeds firm capacity from 2025/26, under both POE50 and POE10 | A |
| Gap, 2025/26 | 48 MVA | A |
| Gap, 2032/33 | 791 MVA | A |
| Expected unserved energy, 2025/26 | 5 MWh | A |
| Expected unserved energy, 2031/32 | approximately 2,036 MWh | A |
| Expected unserved energy, 2047 | 11,307 MWh | A |
| Transformer repair duration assumed | 72 days | A |
| Consequence of a contingency | Load shedding required to hold load below the firm capacity of remaining in-service transformers | A |
| Supplying 330 kV lines | Seven. Three north (20, 26, 29), three west (32, 38, 39), one south (30) | A |
| Referenced operating limit | 1,500 MVA at Sydney West BSP | B |
Two separate regulatory processes are in play. Conflating them is the most common error in this story, and it consistently makes the site look better than it is.
| Preferred option | New 375 MVA 330/132 kV transformer at existing Sydney West BSP A |
| Capital cost | $24.78m ±25% ($2022-23) A |
| Commissioning | 2027/28 A |
| Alternative | New 330/132 kV BSP at Mt Druitt, convert lines 932 and 219 to 330 kV B |
| Net effect | Closes under half the existing deficit, before this project is added |
| Identified need | Flows exceeding Macarthur 132 kV BSP capacity, potentially from 2026/27 under transformer outage A |
| Capital cost | $136.7m ($111.7m Transgrid + $25.0m Endeavour) A |
| Net market benefits | approximately $600m present value A |
| Delivery | Six years, commissioning 2029/30 A |
| Environmental approval | REF exhibited 11 Jun to 10 Jul 2026 A |
| Scope | Aerotropolis distribution growth, not a gigawatt transmission connection at Sydney West |
From Transgrid's letter to data centre proponents of 17 June 2026, signed by the Executive General Manager, Network.
| Measure | Value | Grade |
|---|---|---|
| Prospective DC load in advanced discussions | More than 8 GW | A |
| NSW average daily demand, Transgrid's own comparator | 7.5 to 10 GW | A |
| Connection agreements already signed, Western Sydney | approximately 1.5 GW, accommodable near-term | A |
| Enquiries within 12 km of Sydney West since late 2024 | 14 GW, equated by Transgrid to NSW peak winter load | B |
| Capacity position | Largely exhausted beyond 2033 | A |
| Who funds augmentation | Proponents that trigger the need or benefit, funded upfront | A |
| Cost exposure for this site | Requires network study. Not inferable from public data | n/a |
| Indicative time to full 1 GW connection | Contingent on augmentation that is neither designed nor funded, and on major transmission projects Transgrid describes as uncertain in timing | C |
These fields are marked, not graded. Assigning even a D would imply a basis that does not exist, and a connections engineer would spot it immediately.
Each of these is a live question for a load of this size. None is answerable from a TAPR, a RIT-T or a hosting capacity map.
| Fault level and short-circuit headroom | Requires the network model and a fault study at the specific connection busbar. Not published at any granularity. |
| System strength | Requires assessment against the NER system strength framework, considering the specific converter technology and its interaction with local synchronous plant. |
| Transient and voltage stability | Requires dynamic simulation of the actual connection configuration and load models. |
| Protection coordination | Requires the protection scheme design, settings and grading study for the lead-ins and the BSP. |
Nothing, and that is the point. The scorecard already grades Grid Headroom 1.1, available capacity in zone, as Severe, which holds the pillar in its bottom band under the Critical Sub-Indicator Rule and caps the site at 39, High-risk. This deep-dive does not move the score. It evidences it, at a level of specificity a connections engineer can argue with.
| The scorecard says | The deep-dive says |
|---|---|
| "No spare capacity for a gigawatt-scale load" | Firm capacity deficit of 48 MVA in 2025/26 growing to 791 MVA by 2032/33, against a committed remedy of 375 MVA |
| "Requires major network augmentation" | Which BSP, which RIT-T, what it cost, when it commissions, and why the one everyone cites solves a different problem |