LVI Rubric v0.3 · Scored 6 Aug 2026 · Public record only
0
LVI out of 100
 

Kurri Kurri Data Centre

Hart Road, Loxford NSW · Cessnock City LGA · SSD-128819490
540 MW · 21 ha · Status: Prepare SEARs, not yet exhibited
Former Hydro Aluminium Kurri Kurri smelter, remediation substantially complete · Applicant ADW Johnson Pty Ltd

Critical Constraint Cap: Not triggered

Raw pillar sum is 75.0 and no pillar sits in its bottom band. No critical sub-indicator scores Severe, so the cap does not fire and the LVI equals the raw sum. The decisive difference from Mamre Road is location: this site is outside the Western Sydney transmission bottleneck entirely, on land that already carries heavy industrial power infrastructure.

⚠ Latent Opposition Flag: Raised

Community Licence scores 20.8 on the absence of recorded opposition, not on evidence of support. This application has not been exhibited, so no member of the public has had a formal opportunity to object. Treat this pillar as provisional and treat exhibition as the live risk event. Quiet is not consent.

Raw Sum
75.0
no cap applied
Final LVI
75
Guarded
vs Mamre Road
+36
39 High-risk to 75 Guarded

The same instrument, two very different answers

Both sites are in New South Wales. Both were scored under LVI rubric v0.3, from the same categories of public source: network operator statements, water authority data, the NSW Planning Portal submissions register, parliamentary records and media. They land 36 points and two bands apart.

MetricMamre Road, Kemps CreekKurri Kurri, Loxford
Scale1 GW, 52 ha540 MW, 21 ha
Final LVI 39  High-risk 75  Guarded
Raw sum66.7, capped to 3975.0, no cap
Grid HeadroomCap trigger16.7 / 25
Water Headroom25.0 / 25 (pro-rated, one gap)20.8 / 25
Community Licence12.5 / 2520.8 / 25
Regulatory Clearance20.8 / 2516.7 / 25
Latent Opposition FlagNot raisedRaised
Note the split. Kurri Kurri beats Mamre Road on grid, community and, in practice, on water certainty. It loses on regulatory clearance, because Mamre has confirmed zoning, issued SEARs and an Investment Delivery Authority endorsement, while Kurri Kurri is still at scoping stage on land whose current zoning is not confirmed. An instrument that only ever ranked regional above metropolitan would be encoding a prejudice rather than taking a measurement. This one splits the pillars in both directions, and shows its working on each.

Four pillars, 25 points each

Click a pillar to see the evidence, the confidence rating and the source lineage behind each sub-indicator. This site is at an early planning stage, so several indicators rest on a thin record. The confidence ratings show you exactly where.

Test the score yourself

Flip any sub-indicator and watch the LVI respond, including the cap logic. Sub-indicators marked with a dot are critical: a Severe on one of those holds its whole pillar in bottom band regardless of the arithmetic. Try dropping Grid available capacity to Severe, which is what a refused connection would mean. The cap fires immediately and this site lands in the same band as Mamre Road.

75 / 100
Guarded Raw sum 75.0
Latent Opposition check: Community Licence is in its top band. Under rubric v0.3, where that height rests on an absence of objections rather than positive evidence of support, the scorecard must carry the Latent Opposition Flag. On this site it does: the application has not been exhibited, so there is no objection record to read. Quiet is not consent.

Sub-indicators share their pillar's 25 points equally, computed as exact thirds and sixths. N/A items are excluded and the pillar pro-rates across the rest, with the gap flagged. Cap rule: one pillar in bottom band caps the LVI at 39; two or more caps it at 19. A pillar is in bottom band if it scores 6 or below, or if a critical sub-indicator scores Severe.

Data gaps, flagged not hidden

The rubric never assumes best case. This is an early-stage application, so the gap list is longer than on a fully exhibited site. That is a fact about the site, and it is shown rather than smoothed over.

Material, critical indicator

Current zoning of the Hart Road parcel

Not confirmed against the applicable planning instrument or the Portal spatial viewer. The wider holding has been through a rezoning programme and the Department has accepted the proposal as State Significant Development, but permissibility is not directly evidenced. Drives the Mid on zoning fit and is the highest-value gap on the site.

Material

Community response entirely untested

No exhibition, no submissions register, no formal opportunity for anyone to object yet. The Latent Opposition Flag is raised for exactly this reason. This is the single largest unknown in the score.

Material

540 MW on a 132 kV connection

The application nominates connection to an existing 132 kV Ausgrid line. That is a sub-transmission asset and 540 MW is a very large load for it. Whether upstream augmentation is required is unresolved on the public record, and no connection offer or application is visible.

Not read in original

Scoping report

Quoted here via Newcastle Herald and Data Center Dynamics. The document is available in the Portal's Request for SEARs attachments and should be read directly before customer delivery.

Unresolved

Remediation completion status

Described as substantially completed. No site audit statement or completion certificate located. Residual contamination remains a live assessment matter for any EIS on a former aluminium smelter.

Unknown

End user not disclosed

The applicant is a project management firm. The eventual operator is not on the public record, which limits any assessment of proponent track record or delivery capability.

Sources

Every sub-indicator traces to the public record, with its lineage classified as primary, secondary or inferred.